Wachusett Greenways

Connecting the Wachusett Community with Trails and Greenways 

October 2007 Activities

More on Page 2


                              

                                          New construction has begun in Oakham, MA near Muddy Pond.

                        Wachusett Greenways  reconstructed a culvert for the rail trail over a stream from
                     Muddy Pond which was previously washed out when a beaver dam broke some time ago.

                         

                         

                           

                                               Muddy Pond

                 

               Four concrete slabs, donated by Chase Precast were leftovers from the Big Dig in Boston and will be the base for the rail trail bed over this culvert. The concrete blocks were donated by R.J. Paquette. Bob Salvadore is the contractor.

                                        

                         Left to right: Ed Yaglou, Joe Davenport, Bob Salvadore, and Bruce Pennino

 

           

                                                         Finished culvert in Oakham at Muddy Pond